Practice Problems
Draw a network diagram for the following activities:
Activity Time (days) 1-2 3 1-3 2 2-4 4 3-4 5 4-5 6 Construct a network diagram and determine the critical path for the following activities:
Activity Time (days) 1-2 2 1-3 3 2-4 5 3-5 6 4-6 2 5-6 3 Develop a network diagram and find the earliest and latest start and finish times for each activity:
Activity Time (days) 1-2 4 1-3 3 2-5 7 3-4 6 4-5 2 5-6 8 Draw the network diagram and calculate the total project duration and slack time for each activity:
Activity Time (days) 1-2 3 1-3 2 2-4 6 3-5 5 4-6 4 5-6 7 Construct a network diagram for the following project and determine the float for each activity:
Activity Time (days) 1-2 5 1-3 6 2-4 3 3-5 7 4-6 2 5-6 4 Develop a network diagram and use the PERT method to estimate the expected project completion time. Use the formula:
Given optimistic (O), most likely (M), and pessimistic (P) times:
Activity Optimistic (O) Most Likely (M) Pessimistic (P) 1-2 2 3 5 1-3 3 5 7 2-4 4 6 8 3-5 2 4 6 4-6 5 7 9 5-6 3 5 7 Draw a network diagram and compute the critical path for the project using the following activities:
Activity Time (days) 1-2 2 1-3 3 2-4 4 3-5 5 4-6 6 5-6 2 Prepare a network diagram and determine the earliest and latest start and finish times for each activity. Identify the critical path:
Activity Time (days) 1-2 3 1-3 5 2-4 2 3-5 4 4-6 7 5-6 3 Construct a network diagram and calculate the total project duration and slack for each activity:
Activity Time (days) 1-2 4 1-3 2 2-4 5 3-5 3 4-6 6 5-6 4 Develop a network diagram and identify the activities that have zero float (critical activities) in the following project:
Activity | Time (days) |
---|---|
1-2 | 2 |
1-3 | 3 |
2-4 | 4 |
3-5 | 6 |
4-6 | 5 |
5-6 3 Click here to buy Click here Click here to buy |
Comments
Post a Comment